Short answer: Most likely yes, but slower and less evenly than in 2026. Flatbed spot rates are still running roughly 30% above last year, and forecasters expect another increase of around 10% in 2027. The pace will depend on how many announced data center projects actually break ground, because only a fraction of the pipeline is under construction today.
If you ship steel, precast concrete, electrical gear or heavy equipment, 2026 has been an expensive year to book open-deck capacity. The reason is not a broad freight boom. Dry van demand has been uneven and housing remains soft. The pressure comes from one place: the build-out of AI data centers and the power infrastructure that feeds them. Here is what the numbers show and what they suggest for the next 12 months.
According to DAT Freight & Analytics, the national flatbed spot linehaul rate averaged $2.60 per mile (excluding fuel) for the week reported on November 16, 2026. That is up $0.62 per mile, or 31.4%, from a year earlier and about 27% above the nine-year seasonal average of $2.05.
The summer peak was higher still. In July, DAT reported spot rates near $2.95 per mile, 44% above the prior year and above the previous 2021 record on a fuel-excluded basis. The autumn pullback is normal construction seasonality, not a collapse.
Contract pricing is now following spot upward. ACT Research reported that September flatbed contract rates were up 18% year over year, while spot was up 29%. Early in the year, contract rates were still down from 2025, so that shift matters: shippers renewing annual agreements are now seeing the increase land in their contracted lanes, not just on the spot board.
Two other signals point to a tight market:
Data center construction starts in the U.S. reached about $84 billion through July 2026, nearly three times the same period in 2025 and close to a quarter of all nonresidential building starts, according to ConstructConnect data. North Carolina and Texas lead the country in year-to-date starts.
The freight impact is large because these projects are material-heavy. DAT estimates that each gigawatt of new data center capacity requires roughly 100,000 truckloads of concrete, structural steel, transformers, switchgear and generators. About 20 GW has been built since 2023 (around 2 million truckloads), and roughly 50 GW is announced for 2026 and 2027, which would mean about 5 million more truckloads in two years. Industry estimates put 50% to 70% of that freight on flatbed or other open-deck equipment.
Freight demand shifts as a campus moves through its 18 to 24 month build:
Because power equipment has long manufacturing lead times, these loads tend to arrive in bursts tied to factory release dates, which creates sudden demand spikes on specific lanes.
In a FreightWaves interview, IntelliTrans executive Blake Azell described the effect as a capacity tax. Hyperscale developers are largely insensitive to freight cost because a late transformer can delay a billion-dollar facility. They pay what it takes to secure trucks, and that pulls flatbed and specialized capacity away from shippers of building materials, metals, chemicals and machinery. Those shippers end up paying elevated rates even though their own freight volumes have not grown.
Capacity is also shrinking on the supply side. Small fleets and owner-operators make up much of the flatbed market, and many have exited since the 2023 to 2025 freight downturn. Tighter driver qualification enforcement has removed further capacity in 2026.
The weight of the evidence says yes, with moderation. C.H. Robinson forecasts that flatbed rates will finish 2026 about 28% higher than 2025 and rise roughly another 10% in 2027, citing manufacturing and data center construction. DAT’s short-term forecast calls for spot linehaul to hold in a narrow range near $2.57 to $2.70 per mile through late December.
The realistic outlook for 2027 looks like this:
Truck First Class provides flatbed trucking services for heavy, oversized and irregular freight across the country, with flatbed, step deck, double drop and RGN equipment. Loads are secured to DOT tie-down standards, routed to meet state oversize requirements and tracked in real time from pickup to delivery. Whether you are moving structural steel to a jobsite or a transformer to a substation, our team can match the right trailer to your load and quote it quickly. Request a flatbed quote today to lock in capacity before the next construction season.
Why are flatbed rates so high in 2026?
Data center construction and related power projects are absorbing flatbed and specialized capacity at the same time that the number of carriers has declined. The result is spot rates roughly 30% above 2025.
How much freight does a data center generate?
DAT estimates about 100,000 truckloads per gigawatt of capacity. A single 500 MW campus can require around 30,000 truckloads of steel, concrete, electrical equipment and generators.
Will flatbed rates go down in 2027?
Most forecasts expect moderate increases rather than declines, around 10% according to C.H. Robinson. Rates could soften on some lanes if a large share of announced projects is delayed or canceled.
What trailer do data center transformers ship on?
Large power transformers usually ship on double drop, RGN or multi-axle heavy-haul trailers because of their height and weight. Smaller electrical gear and switchgear often moves on step decks.